PJM Proposes One-Year Grid Studies for Data Centers and Power Plants

PJM Interconnection proposed cutting the time it takes to study new power plants and data center connections from two years to one, as the largest U.S. grid operator tries to bring new electricity supply online faster.
In a separate filing, PJM proposed requiring large data centers to stay connected through certain grid disturbances after a July incident abruptly shifted nearly 3.9 gigawatts of demand onto backup power.
PJM filed both proposals with the Federal Energy Regulatory Commission on Nov. 16. The grid operator says it already serves about 10 gigawatts of demand from data centers and other large computing facilities and could add up to 30 gigawatts by 2030. Its July capacity auction for the 2028–29 delivery year left it about 6.8 gigawatts short of its reliability requirement across a system serving more than 67 million people in 13 states and the District of Columbia.
A shorter study, with an annual cutoff
Under PJM’s Fast Energization plan, the grid operator would review applications from power generators and transmission-service requests for large electricity users together. PJM says the combined study would eliminate duplicate work and move financial and project-readiness requirements earlier to screen out speculative applications. Some customers could take interruptible service while grid upgrades are built, provided there is spare transmission capacity.
The joint review would also identify which transmission upgrades are driven by large customers and how much those upgrades would cost. State regulators could use that information to decide how much utilities recover from data centers through retail rates. PJM’s transmission owners separately proposed rates and cost-recovery rules for serving large customers.
Data center and power buyers’ groups questioned whether a one-year study would translate into a shorter wait. In an October letter to PJM’s board, the Data Center Coalition and the Corporate Energy Buyers Association said a project that clears its transmission owner’s review just after the annual cutoff could wait almost a year to enter the next cycle, then spend another year in the PJM study.
PJM expects the first application window under the new process to open in late November 2027, subject to regulatory approval. It asked FERC for a 60-day comment period and a decision within 120 days of filing.
Keeping data centers on the grid
PJM’s second filing would set voltage and frequency thresholds that large computing facilities would have to withstand while staying connected. The rules would cover sites with peak demand of at least 50 megawatts, including at least 25 megawatts served through power conversion equipment.
PJM is seeking a Jan. 16, 2027, effective date. New facilities would have to demonstrate compliance to connect and operate. Existing facilities would have one year from the effective date or one year from the start of commercial operation, whichever comes later.
The proposal follows a July 22 transmission fault in Northern Virginia that triggered two waves of data centers switching to on-site generators. The abrupt drop in demand caused swings in voltage and frequency, prompting PJM to reduce generation to rebalance the system. PJM said it was the largest unexpected transfer of demand to backup power in its history.